Milestone 6

CSC 333 Project Status Report                                                                                  

Project Name: HELP
Team Members: Dave Hess, Robert Lusk, Ria Ghose

Team Lead: Robert Lusk

Date Report Submitted: May 4, 2004
Time Period Reporting On: April 22 – May 4

1.      Progress Made

Several bugs from milestone 5 have been fixed

·        The report prints out

2.      Future Plans

We will be handing over this DB to HELP. Current plans include transition, training and user manual.   As well as a short document detailing our plans for the Application to aid in future extension of the DB.

 

3.      Issues Resolved

The basic functionality of taking in client information and printing reports based on this information can be done using this DB.

 

4.      New Issues to be Addressed

There is still a need for the intake form to be streamlined, taking out some of the manual selection’s for the client for each page and make it work as one seamless form.

 

 

 

 

 

 

 

 

 

 

 

 

Milestone 6 Completion Document

Milestone Completion Summary for CSC333 (Spring, 2004)

 Milestone Number: 6

Team Name: HELP ministries

Team Members (and Roles, including leader):

Dave Hess: — Fixing Bugs with intake forms.

Robert Lusk: (Lead)—Report creation and bug fixing

Ria Ghose: --  Documentations, Final presentation.

Due Date: 2004-5-04

Summary of Results of Milestone: 5

·        The current DB intakes client information through a series of forms

·        Reports can be generated based on these intakes, which show all the information for a client.

Strengths of Milestone: 6

·        The database represents the basic functionality used by HELP for taking in client information. The DB allows them to search for clients, perform queries, and generate reports of a clients stored information. 

Weaknesses of Milestone: 6

·        HELP will not use the current DB right away. There are parts of their current database application that would need to be implemented before they make the transition to the new application.  Their plan is to slowly develop this new Database on the side, and then take the time to make the transition when it is completely functional.

Project Status:

       Green – Yellow

 

Effort:

Bug Fixing— Dave,

Test Plan—Ria and Dave

Final Presentation-- Ria and Bobby

Reports-- Bobby

Completion Summary and meeting notes—Ria

Response to M5 feedback—

Creating CD-ROM-- Dave