Project
Name: HELP
Team Members: Dave Hess, Robert
Lusk, Ria Ghose
Team
Lead: Ria Ghose
Date
Report Submitted:
Time Period Reporting On: March 2nd March 11th
1.
Progress Made
We now have a UML data model showing the major
working of the system. This helps us gain a better understanding of the system.
We have been able to incorporate some of the items requested by HELP into the
data model, like the drop down menus. The business rules also add a new
standard to the project, besides they abide by the HELP requirements.
Our low-fidelity prototype gives us an understanding
of how the system will look like once implemented.
2.
Plans for
Upcoming Time Period Until Next Status Report Due
We will begin work on milestone 4. We will focus on
the deliverable of increment 1 which includes creating the physical database.
At this point we will also work on designing the GUI.
3.
Issues Resolved
The entities in our table clear the way for physical
database design. Our issue with creating a separate person and client table
have been resolved (fro details see UML diagram).
4.
New Issues to
be Addressed
Although we have tried to modify the milestone 2 for
the functional requirements, we are not sure we have it done correctly.
· Milestone Number: 3
Team
Name: HELP ministries
Team Members (and Roles, including leader):
Dave Hess: (LEAD)Visited HELP and helped with writing the UML Data Model and project update.
Ria Ghose: Documentations, completion summary, business rules, team notes
Robert Lusk: Rework System overview
Due Date:
2004-3-11
Summary of Results of Milestone: 3
We have decided on and
implemented our data model in UML. We have also chosen the technology stack we
are going to be using for the project. We have tried to update and better the
SRS from previous milestone. In addition, we have the following done:
·
We
have an UML data model.
·
A
list of business rules
·
A
data dictionary
·
Low-fidelity
prototype
Strengths of
Milestone: 3
· The UML gives us a better understanding of the system and we can visualize the requirements of the project due to the data model
Weaknesses
of Milestone: 3
·
Our
SRS from milestone 2 is not as strong, even after changes made to it. This may
affect us later on.
Project Status:
Green
Effort:
UML design
Dave
Data dictionary Dave and Ria
Business Rules Dave and Ria
Low -fidelity prototype and database selection Ria,
Bobby, Dave
Project meeting notes Ria and Dave
Completion summary Ria
Modifying SRS Ria and Dave
Updating Website
Dave